Tuesday, 7 May 2013

WEEK 14 : Presentation Day


Process :

v Project functioning as expected
v Poster full with project details and information
v Project successfully presented

Assessor comment :

v Clear presentation
v Project is functioning
v Good presentation Skills




WEEK 13 : Finalize Project


Process :


v Make video as backup to prove the project is functioning
v Design presentation poster
v Print presentation poster

Supervisor comment :

v Video must be made as a prove
v Important content for the poster
v Standby for presentation week







WEEK 12 : Final Troobleshooting and Installation


Process :


v Troubleshoot Circuit component

v Change component value when necessary
v Test the new circuit on breadboard

Problem Statement :

v Some components not suitable
v Some components easily over heat
v Output current too low








Thursday, 4 April 2013

WEEK 11 : Last Minutes Problem


Process :

v Troubleshoot Circuit
v Buy some new component
v Remodel Circuit to avoid some component damaged

Problem Statement :

v Reed switch not functioning
v 1st Piezo Sounder did not produce pulse tone
v 2nd Piezo sounder did not produce sound
v IC and some component damaged
                                                       

WEEK 10 : Build Project Model


Process :

v Draw House Model
v Constuct House Model
v Install Circuit into Model

Problem Statement :

v Need Focus on small house model
v Hard to install circuit inside tiny space







WEEK 9 : Installation Component on PCB


Process :

v Transfer component from breadboard
v Install component on PCB
v Soldering component on PCB

Problem Statement :

v Careless mistakes damaged the component
v Buy some new component for the project





WEEK 8 : Project Testing


Process :

v Construct project on breadboard
v Install component on breadboard
v Using specific tools for small component

Problem Statement :

v Some IC already broke during installation
v Component easily damaged